Finnair Stadium

Additional information

Gross floor area 8 132 m2

Volume 23 700 m3

11 000 seats and 36 box seats

Constructing the project

The construction of the Finnair Stadium was implemented according to a project management agreement.

The construction budget was followed to the letter. Construction employees were given provisions if they were able to keep their costs below the budgeted amount.

The schedule was tight, and thus each party working on the project had to have its tasks defined in a functional way. Trust in functional cooperation was already established in previous construction projects where the same developers worked together.